Rebuilding of 110 kV Golczewo - Recław Power Line

Rebuilding of 110 kV Golczewo - Recław power line - top view - Eltel Networks

Recently, we have been working on the dismantling of the pull-off section 2-6 on the 110 kV Golczewo - Reclaw power line. It is an old German line, the oldest one in the ENEA Szczecin Branch. In the archives of Nowogard City Hall we found information that this line was built in 1938 with a nominal voltage of 30 kV.

The pictures show a span over Szczucze Lake in Golczewo. By using two tall lattice poles, it will be possible to navigate the lake, which was not feasible before.

We would like to thank our colleagues who obtained the owners' consents on the line Maszewo-Nowogard-Golczewo-Recław and at the same time we wish good luck to the team performing the construction and assembly work.

Reconstruction of the 110 kV power line Golczewo - Recław - span over Lake Szczucze in Golczewo - Eltel Networks 110 kV power line Golczewo - Recław - Eltel Networks