Work progress on the 400 kV Laúca-Bita overhead power line in Angola

We are pleased to announce that work is in progress at the construction site of the 400 kV Laúca-Bita overhead power line in Angola, designed by Eltel Networks! The foundations of more than 420 stations were made, almost 310 poles were erected and almost 40 sections of conductors were suspended - this gives a total of 64% of the work performed for this power line. As you can see, the involvement of all companies associated with this project brings successful and productive implementation. Thanks to constant contact with the Contractor, we react to construction reports on an ongoing basis and develop appropriate solutions that take into account the requirements and specific conditions for a given situation.
Thank you all for a good cooperation so far and congratulations on the work progress!